Creating the cloakroom, a start.

After demolishing the larder and cloakroom, it’s time to make a new cloakroom and passageway to the orangery.

Insulation under the floor and new stopcock, pressure reducing valve, anti-knock pipe, provision for water softener and orangery underfloor heating stuff. Next is the cloakroom soil and basin waste pipes now that the radiator is moved and feed pipes for toilet and basin are in and hopefully the right location.

After adding all the underfloor pipes, the joists went in for the new lowered floor area.

Joists for floor.

Floor down, stud work in, pan and cistern plumbed in and working.

Next is the plaster boarding and patch up the wall.

Downstairs cloakroom – demolishing.

Before removing the larder, I had to remove the airing cupboard wall which is supported by the larder. The airing cupboard is a later part of the project!

The lintel supporting the airing cupboard and the one for the door to the old cloakroom where in the main supporting wall so had to be carefully cut out using the Allsaw and drill.